Key Dates
July 20 2026
External Working Group Meeting #1
Project kickoff; baseline analysis and real estate market findings.
July 20, 2026, 3 – 5 p.m. (View the presentation)
September 17 2026
External Working Group Meeting #2
Targeting and opportunity assessment.
Sept. 17, 2026, 3 – 5 p.m. (Location is TBD)
September 17 2026
Community Meeting #1
Project kickoff.
Sept. 17, 2026, 6 – 8 p.m. (Hybrid; Virtual and City Hall, Black-Eyed Susan and Blue Crab conference rooms)
November 12 2026
External Working Group Meeting #3
Implementation framework workshop.
Nov. 12, 2026, 1 – 3 p.m. (City Hall)
November 12 2026
Community Meeting #2
Targeting and opportunity assessment.
Nov. 12, 2026, 6 – 8 p.m. (Hybrid; Virtual and City Hall, Mayor and Council Chambers)
January 14 2027
External Working Group Meeting #4
Implementation strategy refinement.
Jan. 14, 2027, 1 – 3 p.m. (City Hall)